SN | Equipment | Spec. |
A-Steelmaking process equipment | ||
I | Scrap bay | |
40t/10t bridge crane | Lk=22.5m, A6 with magnetic disc | |
16t/3.2t bridge crane | Lk=22.5m, A6 with crab | |
100t rail weigher | ||
80t electrical flat car | Rail distance: 2000mm , Stroke: 30m | |
Scrap bucket | Bottom open V=65m3 | |
Scrap bucket hanger | For scrap bucket | |
3t maintenance hoist | CD1, H=18m | |
II | Melting bay | |
1 | Crane | |
150t/50t double girder metallurgical crane | Lk=26.5m,A7 | |
80t/20t/5t bridge crane | Lk=26.5m,A7 | |
3t maintenance hoist | CD1, H=30m | |
2 | 70t EBT UHP Electric arc furnace | |
Furnace shell | ||
Furnace roof | ||
Seat, platform, tilting mechanism | ||
Maintenance platform | ||
Electrode nippling device | ||
Roof lifting & rotating mechanism | ||
Column | ||
Electrode arm | ||
Water cooled cables | ||
Short net | ||
Furnace transformer | HSSPZ-56000KVA/33KV | |
Series reactor | 9000KVar/33kV | |
H.V. switchboard | GBC-40.5KV | |
L.V. power distribution & cotrol panel | ||
PLC panel | Siemens PLC S7-300 | |
HMI & software | WinCC + Step 7 | |
Hydraulic power pack | ||
3 | 80t Ladle Furnace | |
Roof | ||
Roof lifting & rotating mechanism | ||
Electrode nippling device | ||
Column | ||
Electrode arm | ||
Water cooled cable | ||
Short net | ||
Furnace transformer | HSSPZ-12000KVA/33KV | |
H.V. switchboard | GBC-40.5KV | |
L.V. power distribution & cotrol panel | ||
PLC Panel | Siemens PLC S7-300 | |
HMI & software | WinCC + Step 7 | |
Hydraulic power pack | ||
Ladle car & drawing cable | ||
4 | Furnace auxiliary equipment | |
EAF door lance manipulator | Oxygen: 4000Nm3/h | |
EAF wall lance | Oxygen: 1000Nm3/h, CNG: 300Nm3/h | |
Horizontal ladle preheater | JHK-80-2 | |
Vertical ladle preheater | JHK-80-1 | |
Scrap bucket hanger | ||
80t electrical flat car | Rail gauge: 1435mm , Stroke: 20m | |
Ladle | 80t | |
Ladle hanger | ||
Wire feeder | WX-4BF, double wires | |
Shell sling | ||
EAF refractory gunning machine | ||
5 | EAF materials charging system | |
DRI bin & weighing system | ||
Bulk material bin & weighing system | ||
Auxiliary material hopper & weighting system | 5m3 | |
Conveyor & transportation system | ||
EAF charging hopper & chute | ||
LF charing hopper & chute | ||
Power distribution panel | ||
PLC | Siemens PLC S7-300 | |
III | Casting bay | |
1 | R6m 5 strands billet CCM | 120 sq.mm & 150 sq.mm billets |
Ladle turret | ||
Tundish car | ||
Tundish | ||
Mold | 120 sq.mm & 150 sq.mm | |
Overflow chute & slag pot | ||
Secondary cooling part | ||
Withdrawal straightening machine | ||
Guide roller | ||
Dummy bar | ||
Dummy bar storage device | ||
Flame cutting machine | ||
Cut to length device | ||
Roller after cutting | ||
Billet pusher | ||
Billet storage unit | ||
Power distribution panel | ||
VVVF panel | ||
PLC panel | ||
HMI unit & software | ||
Instrument | ||
2 | Others | |
Off line & maintenance equipment | Tundish rack, mold repairation rack | |
5t Column cantilever crane | R=5m, H=10m | |
50t/10t bridge crane | Lk=28.5m, A6 | |
3t maintenance hoist | CD1, H=18m | |
50t electrical flat car | Rail gauge: 1435mm , stroke: 20m | |
Tundish | ||
Ladle hanger | 70t ladle | |
IV | Billet bay | |
20t/5t bridge crane | Lk=28.5m, A6, one set with grab | |
Billet sling | ||
B-Factory power distribution system | ||
I | Power distribution system | |
H.V. panel | 40.5KV | |
H.V. panel | 12KV | |
Microcomputer protection device | ||
DC panel | DC220V | |
Power transformer | S11 2000kVA, for water treatment plant | |
Power transformer | S11 1600kVA, for main melt shop | |
Power transformer | S11 1000kVA, for oxygen plant, compressor | |
Power transformer | S11 800kVA, for lighting | |
L.V. power distribution panel | ||
Junction box | XLL2 type or XL-21 type | |
C-Air separaton part | ||
I | KDOAr-3200/80Ar air separation plant | Oxygen purity: 99.6% |
Air filter | ||
Precooling unit | ||
Air compressor | ||
Piping after compressor | ||
Cold box | ||
Heater | ||
Expension machine | ||
Oxygen compressor | Pressure: 3.0MPa | |
Nitrogen compressor | ||
Cryogenic liquid pump | Pressure: 3.0/15.0Mpa. | |
Oxyge, nitrogen bottle filing device | 100Nm3/h, pressure: 15MPa | |
Oxygen control valve group | P=3.0MPa/1.6MPa | |
Nitrogen control valve group | P=3.0MPa/1.6MPa | |
Oxygen storage tank | 200m3 | |
Nitrogen storage tank | 100m3 | |
Argon storage tank | 20m3 | |
H.V. switchboard | ||
Starter panel | ||
L.V. power distribution panel | ||
PLC panel | ||
HMI station & software | ||
Instrument | ||
II | Bridge crane | Q=20t/5t, Lk=15m, H=9m |
III | Compressor | |
Water cooled screw compressor | LGD-185/347E type, Q=20m3/min, P=0.8MPa | |
Air holder | C-6/0.8 type, V=4m3;P=0.8Mpa | |
NS energy storage type cold dryer | Q=20m3/min, with purifier | |
D-Fume extraction part | ||
I | Dedusting system | |
EAF canopy & accessory | ||
Canopy pipe | ||
EAF Main fume pipe | 100m | |
LF fume pipe | 30m | |
EAF water cooled fume pipe | 55m Φ1800 | |
LF water cooled fume pipe | 25m Φ700 | |
Fume reversal cylinder | ||
Mixer valve | ||
Regulating valve | ||
Dust collector | 15000m2 | |
Filter bag and bag case | Φ160*6500 , around 4650pcs. per set | |
Dust discharge valve | ||
Dust conveyor | ||
Blower | 60Nm3/h | |
Fluid couplier | ||
Main motor | 1250kW 10KV | |
Chimney | ||
H.V. switchboard | ||
Starter panel | ||
L.V. power distribution panel | ||
PLC panel | Siemens PLC S7-300 | |
HMI station & software | WinCC + Step 7 | |
Instrument | ||
E-Water treatment plant | ||
I | Water treatment system | |
Mold cooling water pump | Q=300m3/h, H=125m, N=160kW | |
EAF & LF, fume duct water pump | Q=700m3/h, H=60m, N=160kW | |
Emergency water pump | Q=600m3/h, H=50m, N=110kW | |
Cooling tower pump | Q=600m3/h, H=25m, N=55kW | |
CCM secondary cooling water pump | Q=180m3/h, H=125m, N=90kW | |
CCM cooling water pump | Q=120m3/h, H=60m, N=30kW | |
Mud circulation clean pump | Q=400m3/h, H=30m, N=55kW | |
CCM secondary sedimentation tank pump | Q=400m3/h, H=40m, N=75kW | |
CCM primary sedimentation tank pump | Q=300m3/h, H=25m, N=55kW | |
Oxygen plant cooling water pump | Q=350m3/h, H=65m, N=75kW | |
Submersible sewage pump | Q=15m3/h, H=12m, N=1.1kW | |
Counterflow type FRP cooling tower | Q=1000m3/h,T1<50ºCT2<35ºC,N=30kW | |
Counterflow type FRP cooling tower | Q=465m3/h,T1<50ºCT2<35ºC,N=22kW | |
Sewage counterflow type FRP cooling tower | Q=300m3/h,T1<50ºCT2<35ºC,N=18.5kW | |
High speed filter | Q=210m3/hV=40m/s, Φ2600mm | |
Automatic pipe filter | Q=1450m3/h, N=1.1kW, PN=1.6MPa | |
Automatic pipe filter | Q=1000m3/h, N=1.1kW, PN=1.6MPa | |
Automatic pipe filter | Q=500m3/h, N=0.75kW, PN=1.6MPa | |
Automatic pipe filter | Q=300m3/h, N=0.37kW, PN=1.6MPa | |
Sediment scraper | Lk=8.3m, H=4.0m, N=~8.0kW | |
Electrostatics water treating device | Q=1100-1399m3/h, DN450, PN=1.6MPa, N<30W | |
Air holder | V=2.0m3, ¢1000mm | |
Water quality dosing device | N=0.75+0.37kW | |
Automatic water softening device | Q=15-20m3/h, water hardness<0.1°dH | |
Slow close/open multi function valve | DN150-400 | |
Float ball valve | PN=1.0MPa | |
Single girder bridge crane | Q=3t, Lk=5m, lift stroke: 6m | |
Single rope grab | V=0.5m3 | |
L.V. power distribution panel | ||
PLC panel | Siemens PLC S7-300 | |
HMI station & software | Advantech industrial computer | |
Instrument | ||
Junction box | ||
F-33KV Compensation system(SVC) | ||
SF6 breaker panel | ||
Disconnector | ||
Lightning arrester group | ||
Filter resistance & capacitor bank | ||
Filter reactor | ||
Current transformer | ||
Compensation capacitor | Total capacity: 75MVar | |
TCR & control unit | ||
Wall bushing | ||
Busbar | ||
L.V. panel | ||
PLC & HMI | Siemens PLC S7-300 | |
Pure water device | ||
Accessory | ||
G-Quick laboratory equipment | ||
Rapid sample cutter | ||
Bench driller | Max. drilling hole: Ф15mm | |
Automatic milling machine | ||
Grinder with dust collector | Wheel dia: Ф200mm | |
Infared CS analyzer | Measuring: c:0.002~3.0% s:0.002~0.35% | |
Vacuum direct read spectrolab | Wave length: 130~850mm, 15 channels |